§ 13.01.140. Resubmittals and expiration of approvals.


Latest version.
  • (a)

    A maximum of six (6) months will be granted to applicants to resubmit incomplete application packets. Any project that is inactive for six (6) months or more must be resubmitted with new submittal information and fees. Failure to meet this six-month time line will result in applications becoming permanently inactive and the applicants forfeiting their fees.

    (b)

    Approval by the Town Council, Planning Commission, or Planning Director of any site plan or use by special review shall remain in effect for a period of twelve (12) months. Any approval of an application for which a grading permit or building permit has not been issued or for which the use by special review has not commenced within twelve (12) months after approval of the site plan or use by special review shall be null and void. An extension of time of up to ninety (90) days may be granted by the Planning Director for good cause. Any denial of the extension may be appealed to the Town Council. If denied, the applicant may resubmit a new application and fees for the same project.

    (c)

    Upon denial of any land use application, the same or similar application, as determined by the Planning Director, may not be resubmitted for a period of six (6) months commencing from the date of denial. The determination of the Planning Director may be appealed to the appropriate body in writing within ten (10) working days of the Director's decision.

    (d)

    Responsibility for complete and proper application submittal shall be that of the applicant. Failure to do so will result in a delay or denial of the application. Furthermore, if any documentation presented to the Planning Department is found to be fraudulent, the application will be denied or approval revoked.

(Ord. 3.01.111 §1, 2017; Ord. 3.01.84 §2, 2008; Ord. 3.01.7 §1, 1995)